Dates (From - To)
|
Client
|
Description Of the Contract/Mission
|
Tasks And Responsibilities
|
|
March 2025 – ongoing
|
Model Slovenia SHPK
Reference: Afrim Tafa – Drejtor
Mob: 0038348545554
[email protected]
|
Architect-Manager
|
Assignment:
Residential Apartment complex, 12,000.00 m2, “MAT1”, Prishtinë.
Description of services: The design of the entire complex with all architectural phases: architectural, structural calculation, water and sewage installations, electricity, HAVC, building physics. as well as obtaining building permit in the Prishtina Municipality.
MUNICIPAL ENVIRONMENTAL PERMIT REPORT.
Legal basis for drafting the
report; Work methodology; Description of location and environmentbaseline; Description of the buildings and technological process; Environmental impact report for municipal environmental permit; Air pollution, Water pollution, Soil pollution, Noise, Effects on
|
|
Januar 2025 ongoing
|
Model Slovenia Invest
Reference: Shpetim Memishi – Manager
Mob: 0038349654131
[email protected]
|
Architect-Manager
|
Assignment:
Residential Apartment complex, 31,000.00 m2, “Kalabri”, Prishtinë.
Description of services: The design of the entire complex with all architectural phases: architectural, structural calculation, water and sewage installations, electricity, HAVC, building physics. as well as obtaining building permit in the Prishtina Municipality.
MUNICIPAL ENVIRONMENTAL PERMIT REPORT.
Legal basis for drafting the
report; Work methodology; Description of location and environmentbaseline; Description of the buildings and technological process; Environmental impact report for municipal environmental permit; Air pollution, Water pollution, Soil pollution, Noise, Effects on
|
|
August
2024
|
The Kosovo Energy Efficiency Fund - KEEF
|
Energy auditor
|
Assignment:
Cert.no.18. Public Calls 2024
Kosovo Energy Efficiency Fund announces a Public Call for implementation of the Emergency Project “Implementation of energy efficiency measures for individual residential houses”
Audit of more than 10 individual houses that have benefited from subsidies
|
|
Januar 2021- September 2022
|
Model Slovenia Invest
Reference: Shpetim Memishi – Manager
Mob: 0038349654131
[email protected]
|
Architect-Manager
|
Assignment:
Residential Apartment complex, 22,000.00 m2, “MAT1”, Prishtinë.
Description of services: The design of the entire complex with all architectural phases: architectural, structural calculation, water and sewage installations, electricity, HAVC, building physics. as well as obtaining building permit in the Prishtina Municipality.
MUNICIPAL ENVIRONMENTAL PERMIT REPORT.
Legal basis for drafting the
report; Work methodology; Description of location and environmentbaseline; Description of the buildings and technological process; Environmental impact report for municipal environmental permit; Air pollution, Water pollution, Soil pollution, Noise, Effects on
|
|
Januar 2021- September 2022
|
Model Slovenia
Reference: Afrim Tafa – Drejtor
Mob: 0038348545554
[email protected]
|
Architect-Manager
|
Assignment:
Residential Apartment complex, 16,000.00 m2, “Kalabri”, Prishtinë.
Description of services: The design of the entire complex with all architectural phases: architectural, structural calculation, water and sewage installations, electricity, HAVC, building physics. as well as obtaining building permit in the Prishtina Municipality.
MUNICIPAL ENVIRONMENTAL PERMIT REPORT.
Legal basis for drafting the
report; Work methodology; Description of location and environmentbaseline; Description of the buildings and technological process; Environmental impact report for municipal environmental permit; Air pollution, Water pollution, Soil pollution, Noise, Effects on
|
|
July - August 2024
|
F.C. Pristina Reference:
Reference: Arton Osmani- director
|
Project manager, architect
|
Types of activities:
Architect for the second phase of the conceptual and detailed design for the construction of the training camp for the Football Club Prishtina.
|
|
July - August 2024
|
F.C. Pristina Reference:
Reference: Arton Osmani- director
|
Environmental Expert
|
Types of activities:
The preparation of the report for the Environmental Permit for the sports facilities of the "Prishtina" Football Club, including: the stadium with changing rooms and stands, the auxiliary fields, the hotel, and other auxiliary spaces in a total area of: S=100,000.00 m²
|
|
March-Jun
2024
|
EBE Energy SH.P.K.
Reference: Festim Syla-manager Email: [email protected]
|
Environmental Expert
|
Types of activities:
Preparation of the Environmental Impact Assessment (EIA) report for the 3 MW "Mjellma 2" solar park project in Shtime by the investor EBE Energy. The service included the drafting of the EIA report, conducting the public discussion, and obtaining the environmental consent from the Ministry of Environment and Spatial Planning.
|
|
June -August
2024
|
RAFFI SH.P.K.
Reference: Ehat Bytyqi Tel.no: 00383 44 506 037
|
Energy auditor
|
Types of activities:
Feasibility study of 135 MW solar farm in Cermjan-Gjakova, for the investitor RAFI Sh.P.K.
ESIA,Technical Analysis. Site Suitability, Solar Resurce Assessment, Pawer Demand Assumptions, System design, Performance Analysis, Cost Analysis, Financial IncentivesReturn on Investment.
|
|
Januar 2023- September 2024
|
Limit Project Sh.P.K.
Reference: Lulzim Zaraj – Owner
Mob: 00383 45 401 976
[email protected]
|
Architect-Manager
Environmental expert
|
Assignment:
Residential Apartment complex, 15,000.00 m2, “Prishtina e Re”, Prishtinë.
Description of services: The design of the entire complex with all architectural phases: architectural, structural calculation, water and sewage installations, electricity, HAVC, building physics. as well as obtaining building permit in the Prishtina Municipality.
MUNICIPAL ENVIRONMENTAL PERMIT REPORT.
Legal basis for drafting the
report; Work methodology; Description of location and environmentbaseline; Description of the buildings and technological process; Environmental impact report for municipal environmental permit; Air pollution, Water pollution, Soil pollution, Noise, Effects on
|
|
June/ 2023-
Sep/ 2023
|
Kosovo Energy Corporation - KEK
Reference: Donjeta Sgogojeva, Project Manager,
email:[email protected];
tel:+38344229106
|
AEK group SH.P.K & Lorenco SH.P.K.
Lead ESIA
|
Assignment:
Environmental and Social Impact Assessment (ESIA) for the solar PV plant “Kosova A” 100MW.
Types of activities:
Mobilisation of a team of qualifies experts to undertake ESIA studies. Describe the applicable regulatory requirements and related administrative processes- approval procedure, To propose a stakeholder Engagement Plan (SEP). Prepare an updated version of the Environmental and Social Management Plan (ESMP); Baseline assessment and Impact Analyses related to M&S aspects of Preconstruction and Construction, operation, Decommissioning and Project closure. ESMMP; Public consultation; To support KEK in submitting that eSIA material to the Kosovo Authorities responsible for Environmental permits according to the national regulations in force. Compile, edit and prepare drafts and final versions of project.
|
|
Aug /2023
|
The Kosovo Energy Efficiency Fund (KEEF)
Mob:038 223 776
|
Energy auditor – individual
|
Assignment:
Public Calls 2023
Types of activities:
Kosovo Energy Efficiency Fund announces a Public Call for implementation of the Emergency Project “Implementation of energy efficiency measures for individual residential houses”
Audit of more than 30 individual houses that have benefited from subsidies
|
|
March/2023-
Jan/2024
|
PLANET and consortium
Western Balkans Investment Framework WBIF) - Infrastructure Project Facility Technical Assistance 10 (IPF 10), Infrastructures: Energy, Environment, Social, Transport and Digital economy
Reference:
Dimitris Galanis
Head of Intl Department [email protected]
|
Spatial planning expert
|
Assignment:
Assessment of the potential to deliver utility-scale dispatchable renewable power to Kosovo – Component
Types of activities:
The third phase of technical assistance on this matter (KOS RES III) is envisaged to support the Kosovo Ministry of Economy in implementing the strategic goals concerning RES capacity targets. The work in this phase should include the following tasks:
- Expand the assessment performed in KOS RES II to include suitable publicly owned forested areas.
- Prepare modifications of spatial planning documentation to designate identified locations for RES development.
- Further, analyse the selected locations to prepare those for concession tendering.
The TOR for this project provides the necessary combination of technical, environmental and social, legal, and spatial planning aspects covering a wide variety of issues related to the planning and development of renewable energy projects
|
|
Oct /2021-
Mar/ 2024
|
PLANET and Consortium
Western Balkans Investment Framework WBIF) - Infrastructure Project Facility Technical Assistance 10 (IPF 10), Infrastructures: Energy, Environment, Social, Transport and Digital economy
Reference:
Dimitris Galanis
Head of Intl Department [email protected]
|
LEAD ESIA
|
Assignment:
Kosovo, District Heating Systems: Feasibility Study, ESIA. Western Balkans Investment Framework (WBIF)
Type of services:
The Study covers (9 municipalities) the regions of: Gjilan, Ferizaj, Drenas, Obiliq, Peja, Prizren, Mitrovica, Mitrovica North Zveqan.
The Feasibility Study shall be made based on the results of preliminary work, which include:
- Research, analysis, designs and other expert material;
- Obtaining data for analysis and development of engineering, geological, geotechnical, geodesic, hydrological, meteorological, urban planning, technical, technological, economy, energy, seismic, water management, and traffic conditions;
- Obtaining conditions for environmental and social aspects;
- Obtaining other conditions that affect the construction and use of a particular facility. The Environmental and Social Impact Assessment (ESIA) will: • allow consideration and subsequent decision-making on the appropriateness of the preconstruction, construction, operation and decommissioning of the proposed DH pipeline project;
identify the main types of potentially significant adverse and beneficial impacts associated with the project that will require further consideration and more detailed assessment during the subsequent ESIA process and to set out the scope for any primary or secondary baseline data requirements and assessment methodologies for determining the significance of those impacts.
|
|
2006- ongoing
|
AEK-group
Reference:
Fahrush Azemi, owner, manager,
+38349115324,
azemi [email protected]
|
Managing Director
|
Types of activities:
Managing and implementing different projects to improve the best performance of Energy Efficiency of buildings, ESIA report for: administrative and residential buildings, schools, and health facilities, industrial and other facilities. These projects are implemented by various investore: Private sectors, Government, Municipalities, EU office in Pristina, US Army, World Bank, EBRD etc.
|
|
Dec /2020-
March / 2021
|
HPC international SAS and Earth Active
Reference:
Mimoza Dugolli, manager;
e-mail: mimoza.dugolli@hpc- international.com
mob: +38345898987
|
Energy Auditor and Environmental Expert
|
Assignment:
Prizren Public Buildings Energy Efficiency Project - Category B. Environmental and Social Assessment, EBRD
Types of activities:
- Conducted an Environmental and Social Assessment of the project's impacts and benefits in line with the EBRD Environmental and Social Policy (ESP)
- Developed a Stakeholder Engagement Plan to ensure effective communication and collaboration with all relevant parties
- Prepared the Environmental and Social Action Plan (ESAP) to address identified environmental and social risks
- Created the Environmental and Social Management Plan (ESMP) for construction and refurbishment activities, integrating these plans into the Client's existing management systems and operations
- Coordinated and ensured compliance with the local Environmental Impact Assessment (EIA), including public consultation and disclosure, in accordance with local and national legal and permitting requirements
|
|
Jan /2020-
Jun / 2022
|
Model Slovenia Invest SH.P.K
Reference:
Afrim Tafa, Head of company.
email: [email protected]
mob:0038348545554
|
Project Manager / Architect Engineer
|
Assignment:
Residential Apartment Complex, 22,000 m² – MAT, Prishtina
Types of activities:
- Led the design of the entire complex, covering all architectural phases, including architectural design, structural calculations, water & sewage installations, electrical systems, HVAC, and building physics
- Managed the process of obtaining the building permit from the Municipality of Prishtina
- Prepared the Municipal Environmental Permit Report, including:
- Legal framework and methodology for drafting the report
- Description of the location and environmental baseline
- Overview of the buildings and technological processes
- Environmental impact assessment covering air, water, and soil pollution; noise; and effects on flora and fauna
|
|
Dec/2019-
Oct/2022
|
Model Slovenia SH.P.K
Reference:
Afrim Tafa, Head of company.
email:[email protected]
mob:0038348545554
|
Project Manager / Architect Engineer
|
Assignment:
Residential Apartment Complex, 16,000 m² – KALABRIA, Prishtina
Types of activities:
- Led the full design process: architectural, structural, HVAC, electrical, water & sewage systems, and building physics
- Managed the process of obtaining the building permit from the Municipality of Prishtina
- Prepared the Municipal Environmental Permit Report, including environmental impact assessment and mitigation measure
|
|
Jun / 2019-
Oct / 2019
|
ELSAM sh.p.k
Reference: Saranda Musliu, Head of company
email:[email protected]m
|
Project Manager-Pristina
Environmental Expert EBRD
|
Assignment:
EBRD – grant for ELSAM sh.p.k.
Types of activities:
Feasibility Study for Energy Efficiency and Implementation of Measures at the Industrial Facility, EIA report - Environmental evaluation (present and future energy sources, Emissions, and other environmental impacts as noise). The survey includes collection of information regarding energy consumption, on site visit, measurements for proposed of analyzing energy consumption patterns, identification of energy saving measures, assessing energy saving potential, this through the process of: Identification of production process throughout the facility; Identification of major components (measuring points, control system, production line, layout, luminaires); Inventory of energy consuming and base line calculation; Analysis of energy consumption by type of machine, production line process, and each equipment; Analysis of energy efficiency measures identified, investment cost estimation, energy saving potential and operational cost saving; Identification of the retrofit or control measures including recommendation for intervention in order to improve operational performance of audited installation.
|
|
Jul / 2019-
Apr /2020
|
NOVUS consulting and CSP
|
ESIA and Urban Landscape – expert
|
Assignment:
Prepared the report of the Environmental and Social Impact Assessment - ESIA
Types of activities:
Development of an Irrigation Master Plan and Investment Framework for Kosovo Agriculture and Rural Development Project (KARDP) ESIA Report and Landscape Design
|
|
Oct /2018 -
July /2019
|
Lesna SH.P.K; US army
Reference: Bekim Deshishku, head of company. [email protected]
+38344104104
|
Architect – manager, architect&Energy Efficiency expert.
|
Assignment:
Detailed design of Renovation for primary school “Adem Gllavica”in Lipjan. Energy Efficiency measures, S= 4307. 0 m², according to US Army tender based on SOW.
Types of activities:
Development of the detail designs for the project, identifications of hazardous materials, such is: Asbestos, mercury lamps etc. Responsible for: Detail Design - Architecture phase, preparation of Bill of Quantities, General description, Technical specification, inventory of hazardous materials. Energy Efficiency measures have been taken, such as: EE measures in the building envelope, thermal insulation facades, replacement of doors and windows, insulation of the roofs, renovation of the interior, sanitary joints etc.
|
|
Apr/ 2014-
March / / 2016
|
World Bank & Ministry of Economic Development & Government of Kosovo
Reference: Naim Bujupi, PIU manager
[email protected]
|
PIU - Environmental specialist
|
Assignment:
Kosovo Energy Efficiency and Renewable Energy project
Types of activities:
Responsible for treatment of hazardous materials such is: Asbestos, Mercury lamps. Corporation with the MESP: Responsible for document preparation Framework for the Environmental Management for Hazardous Materials – FEM, Disposal of asbestos containing materials, Treatment of asbestos at the construction/demolition site, Disposal of lead containing dust from removed paint. Disposal of spent compact fluorescent lamps (CFL).
|
|
Feb/ 2016-
Mar/ 2018
|
Eptisa & Novus consulting,
European Union Office
Reference:
Reinhard Knop , team lider e- mail: [email protected];
|
Architect local Expert Supervisor, Key expert
|
Assignment:
“Supervision of Construction and supplies for category I Rendering plant and Administrative Building”.
Types of activities:
Supervision of construction works for administrative building; Supervision of construction and infrastructure works for the rendering plant and administrative building; Supervision of supply equipment for rendering
plant and administrative building. Supervision of Environmental issues such is: Waste water treatment plant and process of work based on Environmental low in Kosovo and EU legislation.
Investor: EU office and Government of Kosovo.
|
|
May/2018 – Jul/2018
|
F&A Inxhiniering
Reference: Afrim Zejnullahu,
Head of Comp.
email: [email protected]
tel:+38349135659
Kosovo
|
Project manager, architect
|
Assignment:
Design, supervision and managing project of residential building with 12 000 m2 in ‘Prishtina e Re’ neighborhood, west area, Prishtina. construction company.
Types of activities:
Prepared MUNICIPAL ENVIRONMENTAL PERMIT REPORT. Legal basis for drafting the report. Work methodology΄Description of location and environment baseline΄Description of the buildings and technological process. Environmental impact report for municipal environmental permit. Air pollution; Water pollution; Soil pollution; Noise; Effects on flora and fauna (Plants and Animals). ENVIRONMENTAL PROTECTION MEASURES
|
|
2018-2019
|
District Heating Gjakova
Position: ESIA lead
Reference: Albana Skivjani,
Acting CEO of Gjakova district
heating.
Albana.skivjani@ngrohtore
|
ESIA Lead
|
Assignment:
ESIA Report for District Heating with biomass in Gjakova
Types of activities:
Responsible for preparing study report of Impact Assessment Social and
Environmental Feasibility Study and ESIA about the change of fuel for
Rehabilitation of the Central Heating System (Heating) in Gjakova.
Non-Technical Approval Rating with Social and Environmental Impact. IPA2011-Infrastructure-Assistance-Project for Western Balkans countries- Technical Assistance 3 Help from Europe/ 131160/C/SER/ MULTI/3C December 2017. IPA 2011-WBIF Infrastructure Project Facility-Technical Assistance3 Europe /131160/C/SER/MULTI/3C. Public Company Organized public debate with the community and different stakeholders for EIA report.
|
|
Apr/2011- Mar/2013
|
Ferizaj Municipality, Kosovo
Reference: Hanife Obrazhda Selimi procurement official Email:[email protected]
|
|
Types of activities:
Manager architect, supervision and responsible for the team of engineers. Ferizaj Municipality, Design projects, prepared bidding documents, of health facilities implementing remedial works in school and health buildings in the region of Municipality of Ferizaj, Measures for Energy Efficiency. Have been made repairs and total renovations windows, facade, roofs etc. of the school buildings.
|
|
Jul/2009-Aug/2010
|
Ministry of Internal Affairs – Gov.Kos
Reference: Fatmir Thaqi, procurement director.
Emai: [email protected]
+38349883017
|
N/A
|
Assignment:
Framework contract
Types of activities:
Development of the detailed designs and supervision for the projects of facilities for the needs of Ministry of Internal Affairs. Responsible for: Detail Design-all phases (Architecture, Static, Hidro, electronic, HAVC, infrastructure); Preparation of Bill of Quantities, General description, technical specification.
Supervision, control of materials, to Technical Acceptance. Have been designed and supervised listed of buildings below:
-Civil Registration Agency in Pristina -Civil Registration center in Gjilan-Civil
Registration center in Lipjan-Civil Registration center in Viti-Civil Registration center in Klina-Civil Registration center in Drenas
|
|
Jun/2010
|
Ministry of Internal Affairs
Gov.Kos.
Investor:
EU Office in Kosovo
Reference: Fatmir Thaqi,
procurement director.
Emai: fatmir.thaqi@rks- gov.net
+38349883017
|
Architect
|
Assignment:
Supply of inventory and equipment for the needs of of the
Ministry of the Interior, EuropeAid/128980/D/SUP/XK
Types of activities:
Prepared Design, technical description, Bill of Quantities (BOQ)
|
|
Jul/2010-Nov/2011
|
Kosovo Centre for Public
Security, Education and
Development
Reference: Tefik Salihu,
procurement director
[email protected]
|
Project Manager
|
Assignment:
Polygon for shooting exercise
Types of services:
Detail Design & Supervision-all phases (Architecture, Static, Hidro, electronic, HAVC, infrastructure).
Preparation of Bill of Quantities, General description, technical specification.
Supervision, control of materials, to Technical Acceptance
|
|
Jun/2008-Oct/2009
|
Ministry of Internal Affairs –
Gov.Kos
Reference: Fatmir Thaqi, procurement director.
Email: [email protected]
|
Architect Manager
|
Types of services:
Supervision, quality control of materials, Technical Acceptance of Civil
Registration center in Shtime and Kamenica municipality.
|
|
Oct/2007-Dec/2008
|
Municipality of Pristina
Reference: Ekrem Rexha
[email protected].
|
Architect Manager
|
Types of activities:
Detail Design & Supervision-all phases (Architecture, Static, Hidro, electronic, HAVC, infrastructure).
Preparation of Bill of Quantities, General description, technical specification. Supervision, control of materials, to Technical AcceptanceSupervision of Elementary school “Lagjja e Vreshtave” in Pristina
|
|
Jun/2006-Jul/2007
|
Private investitor, Xhelal Idrizaj
Reference: Xhelal Idrizaj
[email protected]
tel:0038344100450
|
Architect Manager
|
Assignment:
The Project Design & Supervision of Norwegian and Finland
Types of activities:
Embassy in Pristina. Preparation of Bill of Quantities, General description, technical specification.
Supervision, quality control of materials to Technical Acceptance
|
|
Nov/2004-Dec/2005
|
Municipality of Pristina
Reference: Ekrem Rexha [email protected].
|
Architect, ACT
|
Types of activities:
The project of public garage in front of the University Clinical Center in Pristina - 40,000 m2
The project of the Kinder Garden “GëzimiYnë” in Pristine
|
|
Mar/2001-Jun/2003
|
Private, Besnik Ramadani
Reference: Besnik Ramadani [email protected]
|
Architect
|
Assignment:
The Project Design & Supervision of Switzerland and France Embassy in Prishtina
|
| |
|
|
|
|
|